VW - Mosel, New construction of Hall 12 |
| Client: | VW Sachsen GmbH, Zwickau |  |
| Contractor: |
Köster GmbH, NL Chemnitz |
| Unit: |
Workshop planning
Manufacture and assembly of the steel construction Tonnage ca 4.000 t
|
| Construction: | 2010 / 2011 |
|
Customer building Audi, Neckarsulm |
| Client: | Audi AG |  |
| Contractor: |
HOESCH CONTECNA SYSTEMBAU GmbH Ed. ZÜBLIN AG |
| Unit: |
Multi-storey car park with 550 parking places
Customer workshop
Customer building,
including elliptical roof and glass façades
Tonnage: ca. 2650 t
|
| Architect: |
BM +P Architekten, Stuttgart |
| Construction: | 2002-2005 |
|
Conference centre, Dresden |
| Contractor: | ARGE Ed. ZÜBLIN AG, Walter-Bau AG |  |
| Unit: |
2 girder grid ceilings with a pent roof - 800 t
3 fire escapes, ca. 33m long - 75 t
Steel, aluminium and glass façade
|
| Construction: | 2003-2004 |
|
Peek & Cloppenburg, Chemnitz |
| Client: | Peek & Cloppenburg |  |
| Contractor: |
Ed. ZÜBLIN AG, Deutschland |
| Unit: |
complete steel construction, including arched roof
Steel, aluminium and glass façade
Volume ca. 550 t
|
| Construction: | 2004 |
|
Ski jumping hill, Klingenthal |
| Contractor: | Vogtlandkreis |  |
| Unit: |
World championship jump to FIS regulations
Construction of the start position completed in steel
Umpire tower
Trainer rostrum
Tonnage ca. 350 t
|
| Architect: |
m2r architecture, London |
| Construction: | 2005-2006 |
|
Inter-city train station at Leipzig/Halle Airport |
| Client: | Deutsche Bahn AG, Deutschland |  |
| Contractor: | Walter Bau AG |
| Unit: |
Workshop planning, manufacture and assembly of an arched, welded, hinged frame with tubed beams as station roofing
Tonnage ca. 600 t
|
| Construction: | 2002 |
|
Civic centre, Bremen |
| Contractor: | Ed. ZÜBLIN AG |  |
| Unit: |
Workshop planning, manufacture and assembly of a new civic centre roof with 85m long chord tube frame (13 pieces) ca. 890 t
Steel entrance foyer ca. 150 t
|
| Construction: | 2004 |
|
New construction of the ThyssenKrupp Stahl-Service-Center, Krefeld |
| Contractor: | ThyssenKrupp – Stahl – Service – Center GmbH, Leverkusen |  |
| Unit: |
New construction of the ThyssenKrupp – Stahl – Service – Center GmbH, Krefeld
Workshop planning, manufacture and assembly of the steel construction of the new hall with canopy
Tonnage: ca. 2.800 t
|
| Architect: |
Stoppacher Ingenieurgesellschaft mbH, Hilchenbach |
| Construction: | 2009 / 2010 |
|
Canopy for the ThyssenKrupp Stahl–Service–Center GmbH, Krefeld |
| Contractor: | ThyssenKrupp – Stahl – Service – Center GmbH, Leverkusen |  |
| Unit: |
Canopy with ca. 30 m projection over water
Tonnage: ca. 300 t
|
| Construction: | 2009 / 2010 |
|
Coil storage hall, TKS - Duisburg |
| Contractor: | ThyssenKrupp Steel Europe AG |  |
| Unit: |
Manufacture and assembly of the steel construction of the hall extension with heavy crane runway
Scale ca. 450 t
|
| Construction: | 2006 |
|
Tubular bridge, TKS - Duisburg |
| Contractor: | ThyssenKrupp Steel Europe AG |  |
| Unit: |
Manufacture and assembly of a heavy media tube bridge for blast furnace 8
Colour-coated metal construction
Tonnage ca. 250 t
|
| Construction: | 2007 |
| Other projects: |
Extension of Hall 10
Heat-treating plant in Duisburg
Scale ca. 400 t
Baujahr: 2005
Extension of walking-beam kiln hall
with heavy crane runway in the Bochum factory
Scale ca. 430 t
Construction: 2006
|
|
"Glück Auf" Tower, Eibenstock / Erzgebirge |
| Contractor: | Eibenstock city council |  |
| Unit: |
Planning, manufacture and assembly of a 35 m high observation tower as a one-piece pre-assembled construction
|
| Construction: | 2007 |
|
Bridge over the River Schwarzwasser |
| Contractor: | The city of Aue / Saxony |  |
| Unit: |
Replacement road bridge after flood damage
Scale ca. 200 t
|
| Construction: | 2003 |
|
Tubular bridge, LEIPA (Schwedt / Oder) |
| Client: | LEIPA paper mill in Schwedt |  |
| Contractor: | RBS Raffinerie – Bau – Schwedt GmbH |
| Unit: |
ca. 950m continuous tubular bridge (in part with 35 m range)
Zinc-galvanised construction
Scale ca. 1050 t
|
| Construction: | 2004 |
|
VW Mosel |
| Client: | VW Sachsen GmbH |  |
| Contractor: | Ed. ZÜBLIN AG |
| Unit: |
New construction of Hall 11 and Hall 6
Manufacture and assembly of the hall structures, preparation of the workshop and assembly planning of the steel construction
Scale: overall ca. 2.100 t
|
| Construction: | 2001 / 2002 |
|
IGOS – Eisenhüttenstadt |
| Client: | The city of Eisenhüttenstadt |  |
| Contractor: | RBS Raffinerie – Bau – Schwedt GmbH |
| Unit: |
Workshop planning, manufacture and assembly of tubular supports and tubular bridge for the paper mill's supply line
Tonnage: ca. 450 t
|
| Construction: | 2009 |
|
Bürstenfabrik Jäckel |
| Client: | Michael Jäckel Erzgebirgische Bürstenfabrik GmbH |  |
| Unit: |
2 halls with 1,500 m² area and 150 t supporting structure in steel
Planning of the structure, assembly and construction
Manufacture and assembly of the shell including the roof and walls
|
| Construction: | 2009 |
|
Erzgebirgsstadion Aue / Saxony |
| Contractor: | Landratsamt Erzgebirgskreis, Annaberg - Buchholz |  |
| Unit: |
Stand roof
Planning, manufacture and assembly of the steel construction, roof and walls
Scale: ca. 100 t |
| Construction: | 2010 |